4.1 Hubei Mobile IDC Data Center Supporting Power System Phase III and Phase I Capacity Expansion Project

☆ Construction unit: China Mobile Communications Group Hubei Co., Ltd

☆ Investment amount: 16.06 million yuan

☆ Construction period: From March 2018 to June 2018

Being is the main construction contents: according to IDC needs of the business departments and professional IDC business requirements, proposed in 2017 xiangyang cloud computing center enable server rack area B IDC room 544, B201 and B202 room by single cabinet 3 kw meter column, B203 and B204 according to single cabinets used 5 kw meter columns, including B201 room should be in accordance with the standard construction, after a week in this engineering power equipment capacity satisfy the December 2017 the professional demand.

Nurture social benefits: this project for power supply safety construction projects, provide strong support to various business requirements, in order to ensure the security of computer room and communications equipment running play a key role, combined with good management and advanced network technology, will give full play to its foundation bearing, is one of the important engineering of xiangyang cloud computing center construction, service for building xiangyang into national hub of cloud computing industry base and data center has played a fundamental role.

 

☆ Technology and management highlights:

1. Adopt 2N dual-bus UPS power supply system. This period adopts online dual-conversion high-frequency UPS equipment, and B201 machine room adopts 2N dual-bus power supply.

2. In the project construction, meet the requirements of energy conservation, emission reduction and environmental protection, pay attention to save electricity, equipment, materials and tools used in the project meet the energy conservation and consumption reduction standards of various related industries;

3. Pay attention to safety management, for dangerous batteries, formulate strict construction procedures, the positive and negative levels of battery wiring, the sealing situation has been strictly checked, the battery test link by professional testers carefully tested item by item;

4, station management, in view of the large amount of xiangyang cloud computing center construction, for a long time, and cloud computing center in xiangyang branch set up project, led by project department technology, head of technical backbone resident at the scene, fully familiar with the environment and management requirements, and the relevant professional cooperate closely, not only greatly improve the efficiency, construction quality and safety has been guaranteed.


8 recordsprev1345678next

5G New Infrastructure

4.1 Hubei Mobile IDC Data Center Supporting Power System Phase III and Phase I Capacity Expansion Project

☆ Construction unit: China Mobile Communications Group Hubei Co., Ltd

☆ Investment amount: 16.06 million yuan

☆ Construction period: From March 2018 to June 2018

Being is the main construction contents: according to IDC needs of the business departments and professional IDC business requirements, proposed in 2017 xiangyang cloud computing center enable server rack area B IDC room 544, B201 and B202 room by single cabinet 3 kw meter column, B203 and B204 according to single cabinets used 5 kw meter columns, including B201 room should be in accordance with the standard construction, after a week in this engineering power equipment capacity satisfy the December 2017 the professional demand.

Nurture social benefits: this project for power supply safety construction projects, provide strong support to various business requirements, in order to ensure the security of computer room and communications equipment running play a key role, combined with good management and advanced network technology, will give full play to its foundation bearing, is one of the important engineering of xiangyang cloud computing center construction, service for building xiangyang into national hub of cloud computing industry base and data center has played a fundamental role.

 

☆ Technology and management highlights:

1. Adopt 2N dual-bus UPS power supply system. This period adopts online dual-conversion high-frequency UPS equipment, and B201 machine room adopts 2N dual-bus power supply.

2. In the project construction, meet the requirements of energy conservation, emission reduction and environmental protection, pay attention to save electricity, equipment, materials and tools used in the project meet the energy conservation and consumption reduction standards of various related industries;

3. Pay attention to safety management, for dangerous batteries, formulate strict construction procedures, the positive and negative levels of battery wiring, the sealing situation has been strictly checked, the battery test link by professional testers carefully tested item by item;

4, station management, in view of the large amount of xiangyang cloud computing center construction, for a long time, and cloud computing center in xiangyang branch set up project, led by project department technology, head of technical backbone resident at the scene, fully familiar with the environment and management requirements, and the relevant professional cooperate closely, not only greatly improve the efficiency, construction quality and safety has been guaranteed.